Iran Moves to Restart West Islamabad Petchem Project after Economic Review

Iran Moves to Restart West Islamabad Petchem Project after Economic Review
(Saturday, September 5, 2026) 08:44

TEHRAN, Sept. 2 (NIPNA)— Iran is moving to resume work on the West Islamabad Petrochemical Project after a review of its technical, economic, operational and social feasibility, according to a member of parliament representing the region.


The restart decision reflects an effort to make use of existing investment and infrastructure while limiting the costs associated with prolonged delays, equipment deterioration and idle capital, Mojtaba Bakhshi-Pour, a member of Iran’s parliament, said.

The GTPP Islamabad West project, with planned final capacity of about 960,000 metric tons of products a year, is one of western Iran’s major industrial projects and the country’s first industrial-scale attempt to convert natural gas into polypropylene using technology developed by Petrochemical Research and Technology Co., according to Bakhshi-Pour.

Construction began in 2019, and the project had reached significant physical progress before its suspension. Considerable investment had also already been made, he said. The recent wartime disruption, combined with accumulated delays, maintenance costs and the opportunity cost of foregone production, increased the economic pressure to determine the project’s future.

Phased Restart

The decision to resume the project followed sustained discussions involving Iran’s Oil Ministry and National Petrochemical Co., Bakhshi-Pour said. The review examined the project’s technical and economic assumptions as well as its execution strategy.

The revised approach calls for maximizing the use of existing equipment and infrastructure, reducing unnecessary costs and completing units in stages to bring the project into production sooner.

Economic assumptions will continue to be assessed against feedstock prices, foreign-exchange rates, capital costs, project schedules and market conditions, Bakhshi-Pour said. Updated assessments indicated that a phased implementation with tighter resource management provides a viable basis for continuing the project.

The approach marks a shift from evaluating the project as a new investment to managing an industrial asset in which substantial capital and infrastructure have already been deployed.

Employment Pressure

The project’s restart also has implications for the local labor market. A significant number of workers were laid off after the project was suspended amid wartime conditions, with many of them young people from the surrounding area, Bakhshi-Pour said.

Resuming construction could bring some of those workers back and support economic activity in Islamabad West, where creating sustainable employment is a major local demand.

Bakhshi-Pour said the project’s importance therefore extends beyond its production capacity, with employment and the development of downstream polypropylene industries forming part of the longer-term rationale for completing the investment.

Existing Investment Under Review

The project has faced criticism in the past over its location, feedstock availability, water supply, product markets and economic viability. Bakhshi-Pour acknowledged those concerns but said the circumstances have changed since the project was originally designed.

The government is now dealing with a partially completed project rather than an investment starting from zero, he said. Existing infrastructure, equipment and physical progress mean that abandoning the project would also carry significant costs.

The restart will be pursued with tighter financial controls, cost monitoring, technical and environmental oversight and greater use of local workers, according to Bakhshi-Pour.

If completed, the project is also expected to provide a platform for downstream polypropylene industries, potentially increasing local value-added production and creating longer-term employment opportunities.

 


Email is required
Characters left: 500
Comment is required