Marziyeh Shah-Daei, project manager of the NPC, said 8 other projects will also come on-stream by March 20 2017 in Iran out of 60 hamstrung petrochemical projects in need of funding in the country.
She said the NPC's priority for finishing the projects is the percentage of their physical progress, adding that projects with at least 60% progress are priorities for completion.
As she said, by the time the 7 envisaged projects for next year complete, Iran will see 2.7 million tons of a year of petrochemicals added to its production capacity. Furthermore, once the other 8 prioritized ones come online some 5.8 million tons of petrochemical products will be added to Iran's capacity as well.
Currently Iran's petrochemical plants can produce 60 mt/y of petrochemicals which is expected to rise to 120 mt/y within the next few years if enough financing of half-finished projects is done timely.