According to the company, implementation of
performance testing began in early April, after the dual furnaces of the plant
were developed, said Hassan Moeini, deputy managing director of the company.
“Given the importance of ethylene production
from gas and propylene, pyrolysis petrol and butadiene from liquid feedstock, this
project was implemented with the aim of increasing the gas and liquid feedstock
by 15 percent,” he said.
The project brought the feedstock supply capacity
of the company from 40 to 46 tons for gas and 50 to 57 tons for liquid
feedstock, he said.
The project would also generate 8 to 10
million Euros in annual revenues for the company, Moeini added.
Jam Petrochemical Complex, with olefin, heavy
and light polyethylene, butadiene and butene 1 production units, is one of the
largest producers of olefins in the world and a major producer of polymer
products in Iran.