Resumption of Utility Supply to Assalouyeh Plants Soon

Resumption of Utility Supply to Assalouyeh Plants Soon
(Sunday, September 18, 2016) 09:02

TEHRAN (NIPNA) – An official with the National Petrochemical Company (NPC) says supply of utilities to the petrochemical plants operating at Asslouyeh Petrochemical Complex, southern Iran, will resume later on Saturday, September 17, 2016.

 

Ali Mohammad Bossaqzadeh, director of production control of NPC, told NIPNA on Saturday that utility supply to the plants will resume after delivery of the utilities was cut after an explosion took over a key pipeline that supplied utilities to the plants. 

The plants had to curtail their production after the incident. 

“We hope the facilities will resume their operation as soon as possible,” he added. 

He said so far 4 generators and the electricity, stream, nitrogen, and water sweetening units of Mobin plant have come online. 

The plant was launched in 2,000.  