TEHRAN (NIPNA) -- Managing director of Lordegan Petrochemical Plant says the project has made 50% progress and is expected to come on-stream by June 2018.

 

Managing Director of the company Mohasen Zarei-Far said the Swiss Ammonia Casale has licensed the ammonia unit of the project while Stamicarbon has vowed to provide the technologies needed for construction of the plant's urea unit.

Financed by a Chinese financier, the project is 15% owned by its stockholder and 85% by the Chinese financier. 

Once operational, the plant will supply 1.073 million tons of petrochemicals annually of which 30% will be consumed domestically and the rest will be sent over to international markets.

The project is being built in 100 hectares of land in Lordegan County in the western province of Charmahal Bakhtiari. 