Construction of Hengam urea and ammonia production project broke a new record in the month of Ordibehesht (the second month in the Iranian calendar year-April 20-May 20) and reached 31.03% progress which was higher than the expected 30.07% progress.
The plant is being constructed with 50% partnership of Indonesia's Pusri company and will process 2,050 ton/day of ammonia and 3,250 ton/d of urea.
Annually, the plant, under construction at Pars Special Economic Energy Zone (PSEEZ), will process 1 million tons of urea and 670,000 tons of ammonia.
Furthermore, Denmark's Haldor Topsoe and SAIPEM have agreed to supply the technical knowhow and licenses for construction of the project.
The plant is expected to come on-stream in a 4-year period and will be fed by the gas recovered from different phases of the supergiant South Pars Gas Field.