Once operational, the unit will bring the plant's annual output from 2.150 million metric tons per year to over 3.3 mt/y.
Phase I of the plant came on-stream in 2001 and its second phase took 6 years to become productive but was not officially launched in 2010.
Pradis Petrochemical Plant runs on natural gas recovered from the supergiant South Pars Gas Field.
The nameplate capacity of the complex's first and second phases is 1.360 mt/y of ammonia and 2.15 mt/y of urea.