Turbines to be Installed at Major Utility Plant

Turbines to be Installed at Major Utility Plant
(Wednesday, January 27, 2016) 11:56

TEHRAN (NIPNA) -- Turbines III and IV of the power unit of Damavand Petrochemical Plant Phase I are scheduled to be installed on Wednesday, January 27, 2016.

Executive director of Damavand Petrochemical Company (DPC) said the two turbines are gas generators and similar models were previously installed at the plant. 
Mohammad-Reza Samiei said the new gas turbines are planned to generate power to Phase II of Assaluyeh petrochemical units which will come online in two years.
The new turbines purchased from Iranian industrial group MAPNA will bring Damavand plant’s nameplate generation capacity to 648 megawatts.
With the installation 12 gas turbines, the total outage of the Damavand plant after completion of three phases will reach 2,000 megawatts, he said.
Phase I of Damavand's generation station is nearly complete and it will come on-stream in the near future.  