Managing director of Mahabad Petrochemical Plant has said linear high and low-density polyethylene is the plant's main product which will be processed at nearly 1,000t/d once the plant comes online.
Mohsen Majidi said beside polyethylene, the plant will produce 30,000 tons of butane every year of which 50% will be exported and the rest will be used for production of polyethylene.
Mahabad Petrochemical Plant is one of the plants along West Ethylene Pipeline which will be fed by the gas recovered from phase developments of the supergiant South Pars gas field.
The plant is constructed with an investment of IRR1,200b.
Furthermore, the polyethylene production unit of the plant is 97% complete and is expected to come online by late September to operate at an annual capacity of 120,000 tons, Majidi said.
He also said 70 to 80% of the plant's output will be exported to destinations overseas.
The plant needs 300,000 tons of ethylene for production of polyethylene annually.
The second phase of West Ethylene Pipeline is close to coming on-stream, project manager at National Petrochemical Company said in April.
Marzieh Shah-Daei said the pipeline is expected to deliver ethylene to Mahabad Petrochemical Plant as feedstock.
She said that the pipeline would provide feedstock to all petrochemical plants on its way.
The second phase of the pipeline is 585 kilometers, stretching from Kermanshah to Mahabad.
West Ethylene Pipeline has the capacity to carry 3.5 million tons of ethylene.