“Someone in Mexico will build a
large polyethylene complex after Ethylene XXI, whether it’s an expansion or a greenfield.
Logic says someone should,” said Jorge Buhler-Vidal, director of Polyolefins
Consulting.
Buhler-Vidal spoke at the
PetroChemical Consulting Alliance seminar ahead of the Latin America
Petrochemical Association (APLA) conference.
Mexico will have a PE deficit, even
after the 1.05m tonne/year Ethylene XXI cracker and polyethylene (PE) project
by Braskem Idesa starts up in 2015. Plus, in the long run, Mexico has the
potential to export to Central American markets, he noted.
Other projects in Latin America are
in the works, but are not expected to come on line anytime soon.
“At some point, Argentina will
develop its shale gas resources and eventually ethylene and polyethylene plants
could be built by 2022,” said Buhler-Vidal.
In Bolivia, state-owned YPFB could
build a 400,000 tonne/year propylene plant by 2018 in Tarija, Gran Chaco, but a
cracker estimated to produce 1m tonne/year of ethylene in Santa Cruz could take
as long as 2022 or later to start up, he said.
“YPFB’s natural gas liquefaction
plant will come on soon, so there will be ethane, but without a customer,” said
Buhler-Vidal.
In Brazil, he estimated that the
petrochemical portion of the Comperj project could start up in 2022, but no
decision has been made yet.
PetroPeru’s planned 1.2m tonne/year
cracker project in Ilo, Peru, “has been delayed for 15 years but is slowly
progressing and will take place”, said Buhler-Vidal. His estimated start-up is
2019.
In the meantime, many countries will
continue to import PE and polypropylene (PP).
“Argentina and Brazil are requiring
more and more PE and PP imports. There has not been new capacity added for some
time, nor will there be,” said Buhler-Vidal.
While Latin America’s macro outlook
is “reasonably good”, with stable or growing economies in Mexico, Peru,
Colombia, Chile Uruguay and Brazil, it is a “high viscosity business climate”,