Mexico’s Ethylene XXI project being built by Braskem Idesa is set to start operations in the fourth quarter of 2015, an executive said on Friday.

“As of the end of October 2014, the project was 85% complete, and in 2015 commissioning and testing will take place. We are targeting a Q4 2015 start-up,” said Cleantho Leite Filho, business development, institutional relations and communications director at Braskem Idesa.

Filho spoke at the PetroChemical Consulting Alliance seminar ahead of the Latin America Petrochemical Association (APLA) conference.

The timing has been moved back slightly from the original start-up date of the end of Q2 2015.

“When we planned the project around five years ago, we were looking at the end of Q2. Now it looks like the beginning or middle of Q4. This is a minimal, reasonable delay compared to our plans in 2010,” said Filho.

Ethylene XXI, a 75:25 joint venture between Brazil-based Braskem and Mexico-based Idesa, will have a 1.05m tonne/year ethane cracker along with two high-density polyethylene (HDPE) units of 400,000 tonnes/year and 350,000 tonnes/year, and a 300,000 tonne/year low-density polyethylene (LDPE) unit.

The project is being built in Coatzacoalcos, Mexico, with around 16,000 workers currently on site, noted Filho.

Braskem Idesa is “ready for another complex” in Mexico, given the projected PE deficit of around 1m tonnes/year by 2020, even after the Ethylene XXI project, he added.

“This all depends on the availability of feedstock, but we’re ready,” said Filho.

The APLA conference starts on Sunday and runs through Tuesday in Rio de Janeiro.

Email is required
Characters left: 500
Comment is required