Iran Steps Up Reconstruction of Damaged South Pars Gas Refineries

Iran Steps Up Reconstruction of Damaged South Pars Gas Refineries
(Monday, November 16, 2026) 15:04

TEHRAN, November 16 (NIPNA) - Iran has launched round-the-clock, three-shift operations at some sections of damaged South Pars gas refineries to accelerate reconstruction and restore lost gas production capacity, Acting Petroleum Minister Hamid Bovard said.

Speaking at a meeting of the Petroleum Ministry's deputies council on Saturday, Nov. 14, Bovard also reported progress in repairing facilities damaged during the recent war, adding that the National Iranian Oil Company (NIOC) and National Iranian Gas Company (NIGC) were overseeing the reconstruction work, Shana reported.

Bovard referred to a recent fire at the Phase 14 gas platform in the South Pars field, saying the incident caused no fatalities and resulted in limited damage, thanks to the timely response of emergency and operational teams.

Following a field inspection of the site, he said specialized and operational personnel were working to repair the damaged equipment and return the platform to production as quickly as possible.

He added that reconstruction at the gas refineries damaged during the war was progressing well, with lost gas production capacity gradually being restored. The ministry expects current production capacity to increase by the end of December.

Bovard called for weekly meetings to monitor production and reconstruction projects, stressing that implementation must continue without interruption.

Funding and accelerated reconstruction

The acting petroleum minister said the ministry was pursuing several measures to expedite reconstruction, including securing the necessary financial resources. He added that permits had been issued to obtain reconstruction funding from banks.

Under the accelerated schedule, some project phases will operate on a three-shift basis to shorten completion times and bring the facilities back online sooner.

Bovard acknowledged the scale of the challenge, noting that some of the gas refineries had taken around four years to build, making their reconstruction within a few months a particularly demanding task. He praised oil industry workers for their efforts in restoring the damaged facilities.

Diesel consumption management plan

Bovard also announced that a plan to manage diesel consumption had been prepared and would be submitted to the government for review and approval.

He said implementation could generate significant savings in domestic fuel consumption and increase the country's petroleum product export capacity.

The plan is expected to reduce diesel consumption by about 20 million litres per day, equivalent to 20%, with the saved volume potentially added to export capacity.

He stressed that revenues generated through fuel consumption management initiatives, including those targeting gasoline and diesel, should be channelled back into the oil industry to help finance development projects, product transportation and other infrastructure requirements.

 

Email is required