According to the public relations of Jam Petrochemical
Plant, Feizollah Beizai, deputy director of maintenance at Jam Petrochemical Plant,
said during the operation, while removing the clogging of the 1022 reactor pump
suction, which is an important step to continue the production of the unit, the
EV-3011 converter was cleaned and the bladder gas holder was replaced.
He said the persistence of the clogging of the reactor
suction was a long-term problem in the continuation of production, and said:
"Fortunately, this clogging has been completely eliminated and now the
reactor is in the production circuit."