According to the company, during its overhaul, the
plant replaced three key convertors used in the production bottlenecks in a
period of 20 days.
Removing main issues with hydrogen compressors for the
first time in the company and replacing C Calm 37101 packings were also included
in the overhaul.
Furthermore, supplying a major part of equipment and
parts that were replaced in the project were also carried out by the company’s
local experts.
Karoon Petrochemical Plant is a major producer of isocyanates
in the Middle East that can be used for production of various items in the petrochemical
industry.