The MTBE
unit of the plant was designed for production of 500,000 tons annually back in
1997 to be developed by UOP. However, imposition of sanctions, the company left
the project which finally came online in 2001.
Since then, for technical reasons and the type of
catalyst used, the unit did not reach its nominal capacity until in December 2017
an agreement was signed with the UOP company to supply catalytic and technical
know-how of MTBE production.
With the implementation of the agreement and the
provision of the main catalysts and the purchase of technical knowledge, the
project for replacing and removing barriers to production was carried out in three
weeks with the presence of UOP specialists.