Addressing a ceremony to launch the project in the southern city of Shiraz, Marziyeh Shahdaei, who is also deputy petroleum minister in petrochemical affairs, said the unit can process 680,000 tons of ammonia and 75,000 tons of granular urea annually.
First Vice-President Eshaq Jahangiri on Tuesday inaugurated the ammonia and urea units of Shohadaye Marvdasht unit of Shiraz Petrochemical Facility.
Minister of Petroleum Bijan Zanganeh and other local officials were present in the ceremony.
Completion of the project cost 550 million euros plus 4,000 billion rials and its operation generates 500 direct and 5,000 indirect jobs, said Managing Director of Shiraz Petrochemical Facility Kianoush Kazemi last week.
Shiraz Petrochemical Plant, the first such facility in Iran, was designed and installed on licenses of Swiss Casale Company and Japan's Toyo Engineering Corporation and Iranian technicians were in charge of the following phases of the project, including detailed and purchasing engineering, tentative operation and operation of the facilities.