Managing Director of the project Hassan Beigi said the plant is being constructed mostly by domestic experts and 5 vessels carrying its needed equipment and machinery will call at Iranian ports in the near future.
Speaking on the sidelines of a visit by National Petrochemical Company (NPC) chief to petrochemical plants in Assalouyeh, south of Iran, Beigi said Iranian manufacturers played an important part in the project's completion, saying the plants is being developed based on the state-of-the-art technological trends.
"We are optimistic that the plant's output will be out in the market during the second half of the current (calendar) year," he said.
The project is being developed for production of 1.650 million tons per year of methanol and has been financed by 0.5 billion euros.
Run on natural gas, the plants will be fed by 5.1 billion normal cubic meters of gas and the utilities supplied by Damavand Utility Plant.