TEHRAN (NIPNA) –- Managing director of Kavian Petrochemical Plant said the plant's second phase will become fully operational once it receives sustainable feedstock by late 2016.

The project will be fed by the ethane recovered from phases 15&16 and 17&18 of the supergiant South Pars gas field, Ramezan Owladi told NIPNA.

He said the plant's first phase was operational last calendar year which ended on March 19.

Owladi said the second phase of the plant is technically operational and is awaiting sustainable feedstock for its official inauguration. 

Kavian Petrochemical Plant can supply over 2 million tons of ethylene annually to be consumed by other plants like Kermanshah, Ilam, Lorestan and Mahabad. 

The ethylene is to be delivered to destinations in western regions of the country by West Ethylene Pipeline. 