Phase 3 of Pardis Petchem Plant 82.72% Complete

Phase 3 of Pardis Petchem Plant 82.72% Complete
(Tuesday, September 22, 2015) 17:01

TEHRAN (NIPNA) – Phase 3 of Pardis Petrochemical Project was 82.72% complete by August 22, 2015.

Construction of the plant began in 1993 with an investment of $220b in its phase 1. Phases 2 of the project started in 2007 and came on-stream in 2010. 

Phase 3 development of the project kicked off in 2011 for production of 380,000 tons of ammoniac and 700,000 t/y of urea. 

In 2010, 51% of the plant's stocks were ceded to Qadir Corporation. However, a major part of the company's shares were sold on the Iranian stock market and the plant is now being owned by Parsian Oil and Gas Company (70%) and Petrochemical Commercial Company (17%). 

The plant is fed by natural gas supplied from the supergiant South Pars gas field. 

Phases 1 and 2 of Pardis Petrochemical Plant process 1.36mt of ammoniac and 2.15mt of urea annually. 