Hengam Petchem Plant 73% Complete in Phase I

Hengam Petchem Plant 73% Complete in Phase I
(Tuesday, June 11, 2019) 17:53

TEHRAN (NIPNA) -- The first phase development of Hengam Petrochemical Plant has made 73 percent physical progress.

During the month of Khordad, which began on May 22, several key parts of the projects were installed including the phase’s primary reformer, ammonia production reactor as well as the CO2 separation tower all weighing over 1,500 tons together.

Moreover, 11 percent of the items needed for completion of the ammonia unit of the project were installed in the facility during the same month.

The plant is being developed for 2,200 tons/day of ammonia production capacity in its first phase and 3,500 tons/day of urea and granule production capacity in its second phase development.

It is being built in Assaluyeh, southern Iran.