Sabalan Methanol Project 79% Complete

Sabalan Methanol Project 79% Complete
(Tuesday, January 22, 2019) 19:21

TEHRAN (NIPNA) -- Construction of Sabalan Methanol Project has so far gained 79% which is only 10% behind the schedule.

The CEO of Sabalan Petrochemical Industries Company, Mohammad Zali, told NIPNA that the project’s backwardness was due to lack of cooperation of its licensor even though all the equipment needed for building it was provided.

He said domestic catalyst providers were to support the project which would accelerate its completion.

Zali said installation and commissioning of the project had gained 51 percent progress, adding the engineering section had progressed 92 percent.

The project is being built in 7 hectares of land in Assaluyeh, southern Iran. Once operational, the facility would supply 1,650 tons per year of AA grade methanol.  